758-meter Hongqi Bridge collapses in Sichuan, China after cracks detected the day before

Part of the Hongqi Bridge partially collapsed this Tuesday (11) in Sichuan province, southwest China, along national highway 317 that connects the center of the country to Tibet. The 758-meter structure, completed in early 2025, was closed the day before by Maerkang police after cracks were detected on nearby slopes and movements in the soil of an adjacent mountain. The collapse occurred due to an aggravated landslide, with no casualties reported, as traffic had already been suspended.
The authorities’ quick action prevented accidents, with all vehicles removed from the scene by late Monday night. Recorded images show the access section and roadbed falling into a ravine, generating a cloud of dust visible from a distance. The incident highlights constant vigilance in areas of high geological instability.
- Main factors identified: deformations on the right slope of the bridge at 5:25 pm on Monday;
- Initial measures: installation of warning signs and evacuation of stranded vehicles;
- Immediate consequences: total interruption of highway 317 in the affected section.
Preventive block details
Alocal police acted based on routine inspections that revealed cracks in adjacent roads and displacements in the mountainous terrain. Engineering teams confirmed the high risk around 6pm, leading to the immediate suspension of traffic in both directions. Until 11pm, the perimeter was completely isolated, with barriers installed to prevent unauthorized access.
Monitoring included preliminary seismic assessments, considering the region’s proximity to the Tibetan tectonic plate. Authorities reported that ground sensors recorded minimal variations, but sufficient to trigger emergency protocols. This response avoided exposing drivers and pedestrians to imminent danger.
Recent construction and opening
The Hongqi Bridge was designed to withstand heavy loads and extreme conditions, with a main span of 220 meters over a 232 meter deep ravine. Sichuan Road & Bridge Group completed construction in February 2025, after years of planning that incorporated high-resistance materials and seismic damping systems. The project was part of national efforts to improve connectivity in remote areas.
Inaugurated in March, the structure facilitated the transport of goods and passengers, reducing travel time by up to 40% for commercial routes. Engineers highlighted the use of advanced steel cables for stability, but the collapse exposes limitations in unstable soils. The construction company issued a note confirming the completion of the works according to the official schedule.
Initial reports indicate that the total cost exceeded 500 million yuan, financed by provincial investments. The bridge wasart of an infrastructure network that includes similar viaducts on the same highway. Before opening, load tests were successfully carried out, validating the capacity for daily traffic estimated at 2 thousand vehicles.
Geological factors involved
Sichuan records frequent seismic activity due to the convergence of tectonic plates, with more than 20 moderate tremors in the last 12 months in the Aba autonomous prefecture. Tuesday’s slide resulted from a combination of recent rains and natural erosion on the slope, worsening pre-existing deformations. Geologists point out that the region accumulates loose sediments, prone to movement after rainfall above 50 mm.
Previous studies identified risk zones along highway 317, leading to the installation of containment networks in neighboring sections. The collapse affected an area of 100 linear meters, with debris scattered across the riverbed below. Rescue teams used drones to map the damage, confirming the partial integrity of the central section.
Emergency and evacuation actions
Stationary vehicles were towed to safe points 5km away, with drivers relocated to alternative routes. Authorities distributed basic supplies to those affected, including water and food, while concrete barriers were erected around the site. Until Tuesday afternoon, access was restricted to engineering and geotechnical professionals.
The contingency plan included alerts via local applications, reaching 15 thousand residents in the neighborhood. Maintenance crews removed initial debris pto avoid additional obstructions in the river. Coordination between police and firefighters ensured the area was fully cleared in less than six hours.
Impact on regional traffic
The disruption directly affects the flow of goods between Sichuan and Tibet, with diversions adding up to 200 km to routes. Truck drivers report delays in deliveries of agricultural products, essential for local markets. Authorities estimate daily losses of 2 million yuan in affected logistics.
Parallel routes, such as secondary sections of the G317, operate with reduced capacity, prioritizing emergency vehicles. Sichuan Road & Bridge Group coordinates inspections of similar bridges to prevent chain incidents. With no defined deadline, reestablishment depends on complete geological assessments.
Highway 317 carries 1.5 million tons of freight annually, connecting industrial centers to pastoral areas. The event reinforces the need for continuous monitoring of critical infrastructures.